We are proud to have supported the TES 2000 Ltd Track Projects team on a highly successful re-railing project at Scout Camp, Brentwood. Despite challenging weather conditions, the works were delivered safely, efficiently, and ahead of programme.
Project Overview The scope of the project involved the re-railing of 1,365 yards of track on the Down Main, using six 709ft rail strings. The works commenced at 02:00 on Sunday morning (Week 35) and were completed within a 25-hour possession. Key activities included:
Technotrack Support Technotrack supplied all required S&T staff, providing:
Safety & Delivery Safety remained the top priority throughout the project. From initial test-before-touch procedures on all plant movements to the careful management of the Brentwood Road Rail Access Point (RRAP), the works were completed with no accidents or incidents. All handback paperwork and stressing documentation were completed and submitted immediately following the shift. A huge well done to everyone involved for maintaining high standards, staying ahead of programme, and delivering quality results in demanding conditions.
0 Comments
Leave a Reply. |
Archives
January 2026
Categories |
RSS Feed